The Hill CountryAddition
From $80,00012 to 16 weeksRoom addition450 sq ft
- Neighborhood
- Alamo Heights
- Final price
- $112,000, with the new roof
- Calendar
- 14 weeks
- Permits
- City of San Antonio, 5 inspections
450 square feet, fourteen weeks, one family at home the whole time.
The Navarros loved their 1962 ranch in Alamo Heights and had outgrown it. We added a garden room off the back in the same cream limestone, with a white oak ceiling and steel windows that open to the live oaks, and put one new standing seam roof over the old house and the new room.
Read more
We drew the plans, filed the permit with the City of San Antonio and were on site for all five inspections. The old porch came down in week two, the slab went in in week three, and the family had dinner in the new room in week fourteen. Marcus sent photos every Friday; these are some of them.
What we build
- Room additions
- Second stories
- Casitas and ADUs
- Kitchen and living room bump-outs
- Outdoor kitchens and covered patios
- Load-bearing walls and structure

The build, week by week
Week 01 · Friday, February 6Site
Friday report: The city approved the plans on Tuesday. Stakes are up, and the level says the yard falls four inches toward the oaks.
Week 02 · Friday, February 13Site
Friday report: The old porch is gone in two days. Its cedar posts are saved for the garden bench.
Week 03 · Friday, February 20Foundation
Friday report: Slab poured Thursday at 6 am, before the heat. First inspection passed.
Week 05 · Friday, March 6Framing & stone
Friday report: Walls and rafters are up. You can stand in the room now and see the oaks through it.
Week 06 · Friday, March 13Framing & stone
Friday report: Every rafter is tied to the slab. Framing inspection is Monday.
Week 07 · Friday, March 20Framing & stone
Friday report: One new metal roof now covers the old house and the new room, on before the rain. The stone comes from the same quarry in Cordova as the house.
Week 08 · Friday, March 27Framing & stone
Friday report: First steel window set today. The rest arrive Wednesday.
Week 09 · Friday, April 3Systems
Friday report: Wiring, plumbing and insulation are in, and all three inspections passed this week.
Week 12 · Friday, April 24Finishes
Friday report: Tile from a family shop in Monterrey, set by hand. The ceiling is white oak, oiled twice.
Week 12 · Friday, April 24Finishes
Friday report: Where the oak meets the stone we left a shadow line instead of trim.
Week 14 · Friday, May 8Handover
Friday report: Walkthrough with the Navarros. Two touch-ups on the list, both done Monday. Keys handed over.
OutsideBefore / After


InsideBefore / After


What construction costs
Every price includes design, permits, inspections and cleanup. Your fixed-price proposal comes after the free home visit.
| Type of work | From | Calendar |
|---|---|---|
| Room additionAbout 450 sq ft | $80,000 | 12 to 16 weeks |
| Kitchen or living room bump-outPush one wall out | $45,000 | 8 to 12 weeks |
| Second storyNew floor over the house | $160,000 | 5 to 7 months |
| Casita or ADUAbout 600 sq ft | $140,000 | 4 to 6 months |
| Outdoor kitchen or covered patioRoof, stone and gas | $25,000 | 4 to 8 weeks |
| Walls and structureOpen a load-bearing wall | $8,500 | 1 to 3 weeks |
From the families we built for
“Every Friday we had photos from Marcus. We watched the room go up from our kitchen table and never had to chase anyone.”
Elena N. · Alamo Heights · Room addition
“Construyeron la casita para mi mamá en cinco meses, con permiso y todo. El precio fue el mismo del primer día.”
Ricardo y Mónica T. · Castle Hills · Casita
“They opened a load-bearing wall in nine days and left the house cleaner than they found it.”
Daniel K. · Monte Vista · Structure
Demo reviews
Building questions
Do I need a permit for an addition?
Yes, and we handle it. We draw the plans, file with the City of San Antonio or your county, and are on site for every inspection, usually five for an addition. Permit fees are listed in your proposal.
Can we stay at home during construction?
Almost always. An addition is built outside the house until the last weeks, when we open the connecting wall behind a dust barrier. We plan the noisy days with you.
What if you find something unexpected?
We open walls and dig only after a close inspection, and the proposal names what could change and what it would cost. If something comes up, you see it and sign the change before we do the work.
How do payments work on a build?
A deposit when you sign, then payments tied to finished stages: slab, frame, systems, finishes and handover. You never pay ahead of the work.
More of our work

Start with a free in‑home visit.
We come to your house, measure, listen and leave you with a list of ideas. No cost, no commitment.