The finished Hill Country addition at dusk: cream limestone walls, black steel floor to ceiling windows glowing warm, a dark standing seam roof and live oaks on both sides.

The Hill CountryAddition

From $80,00012 to 16 weeksRoom addition450 sq ft

Neighborhood
Alamo Heights
Final price
$112,000, with the new roof
Calendar
14 weeks
Permits
City of San Antonio, 5 inspections

450 square feet, fourteen weeks, one family at home the whole time.

The Navarros loved their 1962 ranch in Alamo Heights and had outgrown it. We added a garden room off the back in the same cream limestone, with a white oak ceiling and steel windows that open to the live oaks, and put one new standing seam roof over the old house and the new room.

Read more

We drew the plans, filed the permit with the City of San Antonio and were on site for all five inspections. The old porch came down in week two, the slab went in in week three, and the family had dinner in the new room in week fourteen. Marcus sent photos every Friday; these are some of them.

What we build

  • Room additions
  • Second stories
  • Casitas and ADUs
  • Kitchen and living room bump-outs
  • Outdoor kitchens and covered patios
  • Load-bearing walls and structure
Marcus HaleConstruction leadOn your site every day. Sends the Friday photo report.

The build, week by week

  1. Week 01 · Friday, February 6Site

    Friday report: The city approved the plans on Tuesday. Stakes are up, and the level says the yard falls four inches toward the oaks.

  2. Week 02 · Friday, February 13Site

    Friday report: The old porch is gone in two days. Its cedar posts are saved for the garden bench.

  3. Week 03 · Friday, February 20Foundation

    Friday report: Slab poured Thursday at 6 am, before the heat. First inspection passed.

  4. Week 05 · Friday, March 6Framing & stone

    Friday report: Walls and rafters are up. You can stand in the room now and see the oaks through it.

  5. Week 06 · Friday, March 13Framing & stone

    Friday report: Every rafter is tied to the slab. Framing inspection is Monday.

  6. Week 07 · Friday, March 20Framing & stone

    Friday report: One new metal roof now covers the old house and the new room, on before the rain. The stone comes from the same quarry in Cordova as the house.

  7. Week 08 · Friday, March 27Framing & stone

    Friday report: First steel window set today. The rest arrive Wednesday.

  8. Week 09 · Friday, April 3Systems

    Friday report: Wiring, plumbing and insulation are in, and all three inspections passed this week.

  9. Week 12 · Friday, April 24Finishes

    Friday report: Tile from a family shop in Monterrey, set by hand. The ceiling is white oak, oiled twice.

  10. Week 12 · Friday, April 24Finishes

    Friday report: Where the oak meets the stone we left a shadow line instead of trim.

  11. Week 14 · Friday, May 8Handover

    Friday report: Walkthrough with the Navarros. Two touch-ups on the list, both done Monday. Keys handed over.

  12. OutsideBefore / After

    The same view after: the limestone addition with steel windows and a standing seam roof.
    The back of the house before: stained limestone, an old shingle roof, a worn wood-framed enclosed porch where the garden room now stands and a dead lawn.
  13. InsideBefore / After

    The new garden room: white oak vaulted ceiling, limestone wall, steel windows to the garden and terracotta floor.
    The old enclosed porch: dark paneling, a stained drop ceiling, aluminum windows and worn carpet.

What construction costs

Every price includes design, permits, inspections and cleanup. Your fixed-price proposal comes after the free home visit.

Type of workFromCalendar
Room additionAbout 450 sq ft$80,00012 to 16 weeks
Kitchen or living room bump-outPush one wall out$45,0008 to 12 weeks
Second storyNew floor over the house$160,0005 to 7 months
Casita or ADUAbout 600 sq ft$140,0004 to 6 months
Outdoor kitchen or covered patioRoof, stone and gas$25,0004 to 8 weeks
Walls and structureOpen a load-bearing wall$8,5001 to 3 weeks

From the families we built for

Demo reviews

Building questions

Do I need a permit for an addition?

Yes, and we handle it. We draw the plans, file with the City of San Antonio or your county, and are on site for every inspection, usually five for an addition. Permit fees are listed in your proposal.

Can we stay at home during construction?

Almost always. An addition is built outside the house until the last weeks, when we open the connecting wall behind a dust barrier. We plan the noisy days with you.

What if you find something unexpected?

We open walls and dig only after a close inspection, and the proposal names what could change and what it would cost. If something comes up, you see it and sign the change before we do the work.

How do payments work on a build?

A deposit when you sign, then payments tied to finished stages: slab, frame, systems, finishes and handover. You never pay ahead of the work.

More of our work

A remodeled Spanish colonial house at dusk with a lit arched wooden door and a courtyard fountain

Start with a free in‑home visit.

We come to your house, measure, listen and leave you with a list of ideas. No cost, no commitment.

Book a consultation
Week 1: stakes and orange string mark the footprint of the addition beside the old porch of the 1962 limestone ranch.